Motel Prototype International Motel Firm
8/11/2008
In a continuation of a previous estimating assignment, the prototype configuration of a proposed motel was revised with another estimate being requested by the owner.
Town Border Station Natural Gas Transmission Com
8/8/2008
A pipeline company needed a cost estimate for a town border station on a pipeline expansion project.
Fire Line Electric Utility
8/8/2008
An electric utility company wanted to expand a fire line at one of their sites.
Fire Department Headquarters General Contractor
8/8/2008
A general contractor wanted to bid a design assist project without using subcontractors on the project.
Various commercial Projects Stucco & Plastering
8/8/2008
The contractor needed assistance bidding several projects in a short amount of time.
Street Repair Schedule Paving/Civil Works Contra
8/8/2008
The contractor bid the major reconstruction of a street based upon the traffic being re-routed so all lanes we available at one time.
High Rise Condominium Project - Caulking & Sealing
7/8/2008
A high rise condominium project was bidding, along with a dozen other smaller projects.
Water Discharge Line Electric Utility
7/8/2008
An electric utility company is in the process of upgrading the facility.
Law Enforcement Center Construction Manager
7/8/2008
A construction management firm recently obtained a contract for a new law enforcement center.
Fresh Food Distribution Warehousing Electrical C
7/8/2008
An electrical contractor was asked by their long standing client to provide a conceptual design build estimate on the electrical systems of a distribution warehouse complex.
Manufacturing Facility Mechanical Contractor
7/8/2008
A mechanical contractor needed to bid a manufacturing plant.
Process Piping Scope Evaluation Manufacturing Ow
7/8/2008
A process piping contractor was terminated on a project.
Condominium Mechanical and Electrical Repair/Repla
6/10/2008
A condominium complex was incurred storm damage along one of the coastal areas of the United States.
Assisted Living Center Expansion Prime Contract
6/10/2008
Tempest Company provided feasibility estimates on this project to support the prime contractor.
Family Practice Medical Center Mechanical Cont
6/10/2008
A mechanical contractor had more projects to bid than they could possibly get to.
Power Plant Outage Scheduling Electric Utility
6/10/2008
An electric utility started planning for the upcoming outage over six months in advance of the planned start of the outage.
Fire Station General Contractor
5/7/2008
Tempest Company worked recently on a project in a market where very few bids were being received from subcontractors.
Apartment Complexes Developer
5/7/2008
The apartments required estimates on the construction costs for upgrading and updating the apartments to todays standards.
Prototype Motel Developer
5/7/2008
The new configuration and concept on a nationwide hospitality chain required estimating the project to determine the costs.
Hospital & Medical Center Mechanical Contractor
5/6/2008
The mechanical contractor bidding on a major addition and renovation for a medial project needed the mechanical piping systems estimated while they did the plumbing and sheet metal on the project.
Data Center Addition Construction Manager
4/21/2008
The construction management firm on a large data center expansion project wanted to have an independent opinion on the electrical scope of work and cost at the preliminary design stage of the project.
University Food Service Building University Fa
4/21/2008
Tempest Company prepared a Feasibility Estimate on a proposed dining hall for students.
Regional Headquarters Building Program Manager
4/21/2008
The program manager on a regional headquarters building for a major corporation required an independent estimate of the construction costs.
Specialty Coatings and Finishes Various Projects
4/10/2008
Tempest Company recently completed several projects for a contractor specializing in stucco, exterior insulation and finish systems, along with specialty coatings.
Apartment Complexes National Developer
3/14/2008
Tempest Company has prepared construction cost estimates for renovation and upgrade construction costs for apartment complexes at various locations throughout the United States.
Reheater Replacement Electric Utility
3/14/2008
An electric utility needed to replace the plants reheater unit on the main boiler.
Litigation Support Services Electric Utility
3/14/2008
A large electric utility was involved in a construction dispute on the costs involved to rebuild the precipitators at a coal fire power plant.
Retail Store Prototype National Retailer
2/8/2008
A new store prototype project involved creating a cost template for budgeting future projects with variations in the scope of work.
Activated Carbon Injection Project Electric Util
2/5/2008
A power plant is being retrofitted with activated carbon injection for the control of emissions.
Lighting Contract Electrical Contractor
2/5/2008
An electrical contractor was being selected to install a substantial lighting package at a facility.
Animal Control Facility Architect
2/5/2008
Tempest Companys pre-construction estimating was used by the architect on the project to determine the appropriate budget.
Baghouse Project Industrial Contractor
1/15/2008
Two new baghouses on a power plant were estimated by Tempest Company so the contractor could bid the entire project.
Hospital Addition Electrical Contractor
12/27/2007
An expansion to a hospital by a long term client was an opportunity that an electrical contractor did not want to pass up.
Hospital Project Mechanical Contractor
12/27/2007
A local community hospital was being bid and there was not enough time for the mechanical contractor to prepare their bid without missing other bidding opportunities.
Pharmaceutical Production Plant Expansion Mechan
12/27/2007
The plant expansion bid period was shorter than the contractor could master with their own estimating staff.
Animal Shelter & Hospital Architect
12/27/2007
A regional animal control group needed to expand their facilities due to increased demand for their services and an increase in service area.
Waste Water Treatment Facility Electrical Contra
11/28/2007
A new waste water treatment plant was an opportunity that an electrical contractor did not want to pass up.
Light Commercial, Retail & Residential Estimating
11/21/2007
A small specialty contractor uses our services on an as needed basis for bidding projects.
Cost Studies National Retailer
11/21/2007
Two cost studies were recently completed for a national retail organization.
Feasibility Estimates University System
11/21/2007
Recent assignments for this group include the preparation of estimates on the cost of exterior building configurations.
Feasibility Estimating Electric Utility
11/2/2007
Our services were provided on a system replacement project at a coal fired power plant.
Feasibility Estimating Commercial Building Devel
10/24/2007
A commercial building developer needed the cost to build an office building.
Renovation Estimates Multiple Housing Unit Devel
10/24/2007
A developer of housing units (apartments, condominiums, etc.)need to know the budget to use for the cost of renovating numerous housing sites located through out the United States.
Feasibility Estimating - National Retail Organizat
10/8/2007
A retail chain with operations through out the world was considering concept changes in their retail stores.
Student Dormitory Mechanical Contractor
10/8/2007
As a part of their contract requirements, the mechanical contractor was required to provide an updated estimate on less than 100% design documents for the project.
Hospital Proposal Assistance Construction Manage
8/30/2007
On a recent proposal for a new hospital, one of the firms making the presentation required assistance in developing their presentation materials.
Travel Center Electrical Electrical Contractor
8/30/2007
An electrical contractor faced a problem of bidding multiple projects without having the ability to bid the ones that were required.
Ethanol Facility Mechanical Contractor
8/30/2007
The developers of an ethanol plant needed a guaranteed maximum price from the mechanical contractor to complete the work on a project.
|