The Nine Secrets of Estimating
Don L. Short, II, FCPE
Reprinted with permission of the
American
Society of Professional Estimators
Print This Article
The construction industry has a myth going around. The
myth is that there is a secret to estimating. Well, the myth is misleading;
there are actually nine secrets to estimating! I am about to divulge
to you these nine secrets. As a part of this, I am breaking a decades-long,
perhaps eons long, silence as to the true secrets of successful estimates.
Let the reader beware of the remainder of this article - it may cause
you to question other myths in your life!
FIRST SECRET
The first secret to be divulged is the importance of
the takeoff process in a successful estimate. A successful estimate has
its foundation in a reliable identification of the quantities involved
in the project. Just like a house, if the foundation is no good the house
will fall. It does not matter if the estimate is a feasibility level
estimate or a bid level estimate, the quantities identified must be correct
for the project.
When preparing a feasibility estimate, care must be
taken to identify all of the major and minor cost items in the project
scope. Whether on a square footage basis (or other parametric method),
or a method that uses material quantities, if you do not identify all
of the scope you cannot begin to develop a reliable budget. For example,
a general guide for building construction would be to use the CSI sixteen
division format at levels 1 and 2 for a scope review during the quantity
takeoff period. In the concrete division (level 1), one could identify
the need for concrete on the project. Once this has been identified,
sub-sections (level 2) could be refined further to consider items such
as pile caps, continuous and pad footings, grade beams, slabs on grade,
elevated slabs and equipment or housekeeping pads. By considering these
areas within each of the divisions, a series of quantities can be established
that will form a firm foundation for a reliable estimate.
When preparing a bid level estimate, care must be taken
to identify not only labor and material cost items shown on the plans,
but also labor and cost items that may not be reflected on the plans.
For example, on a plumbing or piping system it is not good enough to
only count the linear feet of pipe by size and material type, number,
sizes and types of fittings, valves and hangers, etc. An estimator needs
to consider the impact of specifications concerning testing, inspection
and start-up activities along with the location of the work. This necessitates
preparing the estimate by system and, perhaps, by area of the facility.
Each system would contain its own listing of materials to aid in determining
the amount of time and materials for testing and related. By identifying
the systems, a reasonably detailed schedule and control budget can be
developed for the construction period without a large amount of time
wasted in their preparation.
Will the takeoff be perfect? "No." There are too many
variables to make any takeoff perfect. However, it will be very reliable
whether it is at the feasibility or bid phase of the project because
the scope of the project has been identified. That is the first secret
of estimating. No one company has a lock on this secret; all of the successful
firms know one of the secrets to a successful project is having a reliable
takeoff.
SECOND SECRET
The second secret is the importance of using labor man-hours
in the estimate. Labor hours, whether developed by crew analysis or applied
on a unit man-hour basis, form another basic part of the foundation of
a successful project. The use of a labor dollar per unit of work (ex:
$15 per cubic yard for grade beams or $20 per cubic yard for walls) is
only applicable when the cost history supports the data being used. For
example, the geographic location is the same, the rate of inflation is
the same, the other project conditions are the same. or in the early
estimates such as a feasibility estimate where a decent cost history
exists for the proposed application.
A lot of firms may think their man-hours are a secret,
but this is not the case. The project conditions (size, location, accessibility,
material sizes and types, erection equipment, etc.) play a major factor
in the determination of the applicable man-hours to be used in an estimate.
What is lesser known, but somewhat acknowledged, is that time and motion
studies show that under specific conditions a skilled person can perform
only so much work efficiently in a given day. This is typically expressed
in a value range such as 100 to 120 units installed in a typical work
period. Time and motion studies also will show under certain circumstances
more total time can be required for one person to perform the work rather
than two persons working together on the item of work.
Projects with incidental amounts of overtime will not
incur any significant productivity adjustments. Projects with extended
periods of 50, 60 or more hours per week will incur substantial losses
in productivity. A second and/or third shift will also incur productivity
penalties.
The labor force for a given project will only perform
within certain ranges of time for specific tasks and the overall project.
An experienced estimator that is applying the man-hours will be able
to judge the conditions that affect the worker productivity on the site
for each item in the estimate. In essence, preparing a range estimate
of time on each item contained in the estimate.
Will the man-hour determination be perfect? "No." There
are too many variables to make any man-hour determination perfect. If
one wants perfect man-hours, let the accountant tally them after the
completion of the project (but then it is too late). No one company has
a lock on this secret; all of the successful firms know one of the secrets
to a successful project is having a reliable determination made of the
hours required to perform the work.
THIRD SECRET
The third secret to be revealed is the hourly rate for
craft labor. A sub-secret to this is the hourly rate for staff labor
and it has similar principals. The labor rate is the cost per hour for
the craftsmen on the project.
To determine any craft rate, whether union or open shop,
the estimator starts with the basic wages and fringe benefits. However,
this is just the starting point. To the wages and fringes, the estimator
needs to add what are commonly called payroll burdens. These burdens
are FICA (Social Security), FUI (Federal Unemployment Insurance), SUI
(State Unemployment Insurance), WC (Worker Compensation) and others mandated
by legislation and/or company operations. These burdens, plus the base
wages and fringe benefits, determine the hourly cost of a craft classification
(ex: a Carpenter, Pipefitter, etc.).
From the point of having the individual craft classification,
the estimator typically needs to develop a crew rate. A crew rate can
consist of a number of journeymen, a foreman and/or a general foreman
or variations on this hierarchy. In this crew there could be ten journeymen,
one foreman and an allocation of a quarter of a general foreman in the
mix. A variable to this mix is that the foreman and general foreman may
or may not be what is termed a "working" member of the crew.
In select cases, where someone is being unrealistically
optimistic on hourly costs, there may be ten "apprentices" and one journeyman
as the crew. This is unrealistic in that the lowered productivity of
the "apprentices" offsets any gains in the hourly rates used in the estimate.
If you don't believe this one, check out how to train people effectively
on the job; it is not a ten to one ratio. Training an estimator is more
of a two or three on one (skilled to beginner) ratio.
The hourly rate can also involve a mixed crew where
a mix of different crafts for a work crew for the performance of the
work. In a case such as this, there may be a crew that is comprised of
six carpenters with four laborers providing support to the carpenters.
It may be a case where there is an operator and a laborer working together.
Overtime or the lack of overtime is another consideration
in determining the calculation of the hourly rates. A project that is
scheduled for completion using a forty hour work week (watch out for
areas that have a standard 35 hour week!) will have a modest amount,
if any, of overtime costs required in the estimate. A project that is
scheduled for extended 50, 60 or even 70 hour work weeks will have a
substantial amount included for overtime and loss of productivity.
Will the hourly labor rate determination be perfect?
Again, the answer is "No." No one company has a lock on this secret;
all of the successful firms know one of the secrets to a successful project
is having a reliable determination made of the hourly rates required
to perform the work.
FOURTH SECRET
The fourth secret concerns material prices.
It is a simple secret, with a potentially complex variable.
The secret is material prices go up and down. The complex
part is the frequency and extent of the price curves.
Prices are affected by timing of the
buying cycle. Does the purchase coincide with a peak or
off time of the year for the manufacturer? This equates
to demand. It also depends upon the size of the order.
Will this be for one standard widget or one thousand custom
widgets? The delivery requirements also affect the price.
If an item with a ten week delivery time frame is needed
in two or three weeks, get ready to pay a big premium.
Payment terms on previous purchases also affect prices.
One big item of material cost are the
sole-sourced items where there are no other brands of
comparable equipment allowed for the project. This creates
a tremendous upswing in the pricing. It is amazing how
someone would allow sole-sourced items in their projects,
if having the best possible level of pricing on the project
concerns them.
Will the material prices in the estimate
be perfect? It is highly probable that "Never" would be
the best answer. However, by recognizing the factors that
raise and lower the costs of materials, it is possible
to get the lowest practical pricing on materials without
resorting to bid shopping or other unethical and possibly
illegal practices. No one company has a lock on this secret;
all of the successful firms know one of the secrets to
a successful project is having a reliable determination
made of the material costs required to perform the work.
FIFTH SECRET
The fifth secret is equipment costs.
Equipment rates are dependent upon the project conditions
to determine the correct size or capacity of equipment
required to perform the work. They are also dependent
upon using the right size or capability of equipment when
interfacing with other types of equipment. With some exceptions,
equipment acquisition and operating costs are going to
be similar for the same conditions of the work, no matter
what contractor is performing the work.
In selecting the right equipment capacity
for a project, consider an extreme example for the use
of a three cubic yard hydraulic excavator versus a .75
cubic yard backhoe/front end loader for excavating a swimming
pool. If the project is to excavate a back yard, shallow
residential swimming pool with tight access restrictions,
the backhoe/front end loader could be a better choice.
However, if it is a regulation Olympic sized pool with
a deep end for diving without any severe access restrictions,
the hydraulic excavator could be the better choice.
When interfacing with other equipment,
cycle times and equipment capacity control the costs on
the project. An illustration of this is mass excavating
and hauling of the spoils. Two basic choices could be
the answer. The first is the use of scrapers to excavate
and haul the spoils to an on-site location. In a case
like this, selecting the correct equipment size would
be a considerable factor since one piece of equipment
can do both tasks. However, if the project conditions
are such that they require the use of hydraulic excavators
with trucks for hauling the spoils, the sizing or quantity
of the excavators and trucks become the primary factor.
If trucking capacity is limited, this will restrict the
size/capacity of the excavator. If the size/capacity of
the excavators is limited, this will restrict the trucking
capacity. In these cases, and others, undersized/oversized
capacity means higher hourly costs and inefficiencies.
Will the equipment costs in the estimate
be perfect? Guess what: another "No!" However, they will
be more reliable by taking these factors into consideration.
No one company has a lock on this secret; all of the successful
firms know one of the secrets to a successful project
is having a reliable determination made of the equipment
costs required to perform the work.
SIXTH SECRET
The sixth secret is subcontractor quotes.
This has components of all the other secrets. A subcontractor
quote contains labor, material, equipment, indirect costs
and profit, just like any other estimate. It is dependent
upon having the quantities, labor hours, hourly rate,
etc., prepared in a reliable manner just like any other
part of an estimate. The amount of the subcontractor quote
is also dependent upon the payment terms like the materials
being purchased on the project.
Will the subcontractor quotes/costs in
the estimate be perfect? Based on the above answers - "Not!" However,
they will be more reliable by taking these factors into
consideration. No one company has a lock on this secret;
all of the successful firms know one of the secrets to
a successful project is having a reliable determination
made of the subcontractor quotes/costs required to perform
the work.
SEVENTH SECRET
The seventh secret is the indirect costs
of a project. Indirect costs are the identification of
labor, material and equipment items required to support
the overall project. Indirect costs associated with a
project range from the overall project costs for the owner
(i.e. design fees, permits, land acquisition costs, legal,
administration, etc.) to the contractor and subcontractor
costs (i.e. mobilization, staffing, temporary construction
and utilities, equipment, small tools and consumables,
etc.).
Will the indirect costs in the estimate
be perfect? "No" again. However, they will be more reliable
by taking these factors into consideration. No one company
has a lock on this secret; all of the successful firms
know one of the secrets to a successful project is having
a reliable determination made of the indirect costs required
to perform the work.
EIGHTH SECRET
The eighth secret is the profit amount.
How secret can profit be on a project? Profit on a project
that has not yet bid is somewhat secret. I definitely
wouldn't let anyone know how much or little profit I was
putting in any bid I was preparing. But the amount of
profit is not too hard to reasonably determine prior to,
or even after, a bid opening by any of the other bidders.
This can't be true can it? Yes, it certainly can!
Let's consider the estimating process
for a minute - the other secrets from above. The quantities
should be similar, and in many cases the same, for all
of the companies. The labor hours to perform the work
should be similar, and in some cases the same, for all
of the companies. The hourly rates to perform the work
should be similar, and in many of the cases the same,
again - for all of the companies. This also applies to
the material and subcontractor prices, and the indirect
costs. Why? Because hopefully the companies are all determining
the estimated cost for the project with the same or a
similar set of project conditions defined in the project
documents! This means the only other significant area
in an estimate is the profit amount.
Successful companies maintain bidding
records. These can be simplistic or sophisticated. On
the simplistic side, the bidding records would indicate
that if Competitor "X" is bidding the project then I should
pass on this project because "X" always has a lower price
than I can bid. On the sophisticated end of bid analysis,
the records should be analyzing labor, material, equipment
indirect costs, etc, along with profit. From the overall
perspective, historical determinations can be made as
to profit amounts. If a company has a cost basis similar
to their competitors (this should be the case, but there
are exceptions), the profit of their competitors can be
determined with a reasonably high degree of certainty
after a project has been bid. By analyzing historical
trends in the bidding process, one can determine, with
a reasonable amount of certainty, the likely amount of
profit on an upcoming bid by the competition.
NINETH SECRET
The ninth secret is that there are no
secrets in estimating! Well, perhaps for one estimate
or two, but then again, that's a different story!
P.S. There is a tenth secret! I kept
it out of the title on purpose. The tenth secret is that
all of the successful companies use experienced, professional
estimators to determine the estimated costs of a project.
This includes estimates at the feasibility, schematic
design, design development, construction documents and
bid phases on a project. Professional estimators use all
of their knowledge and skills in knowing and understanding
these estimating "secrets" and their applicability to
each and every project. Does this mean they will always
be low if they are a bidder? Watch out - the answer is
another "No!" Does this mean they have the right "amount" for
the project? It is highly likely that this is a resounding "YES!"
P.P.S. There is a eleventh secret that
I absolutely will not divulge - the secret handshake of
professional estimators! You will have to become a member
of the American Society of Professional Estimators to
find out this secret!
Print This Article